This MXN 5.8 bn (~USD 317 m) contract supplies new rolling stock for the AIFA–Pachuca — CRRC 15 Electric Trains programme in Mexico. The fleet operates on ERTMS Level 2 signalling and 1435 mm standard AIFA–Pachuca Train (Mexico City–Pachuca Corridor) · Tren Interurbano México–Toluca (El Insurgente) — Full Line · Tren Maya (Mayan Train) — Full Network · News
AIFA–Pachuca Rolling Stock — CRRC 15 Electric Trains is a commuter rail project in Mexico, currently procurement.
This MXN 5.8 bn (~USD 317 m) contract supplies new rolling stock for the AIFA–Pachuca — CRRC 15 Electric Trains programme in Mexico. The fleet operates on ERTMS Level 2 signalling and 1435 mm standard gauge. ARTF is delivering the project, with CRRC Zhuzhou as main contractor. Target opening is 2027, with an investment of MXN 5.8 bn (~USD 317 m).
Construction began in 2025, with completion expected in 2027.
The project has an estimated investment of MXN 5.85B.