This 5.5 km tram line is under construction in Poland. It comprises 70 km/h design speed. The line uses 750 V DC overhead electrification and 1435 mm standard gauge. Zarząd Inwestycji Miejskich Kraków Poland Łódź Railway Hub Modernisation · PKP PLK · News
Krakow Fast Tram KST Stage III (Krowodrza Górka – Górka Narodowa) is a tram project in Poland, currently under construction.
This 5.5 km tram line is under construction in Poland. It comprises 70 km/h design speed. The line uses 750 V DC overhead electrification and 1435 mm standard gauge. Zarząd Inwestycji Miejskich Kraków is delivering the project, with Intercor and Tor-Krak as main contractors. Under construction since 2022, the line is scheduled to open in 2026, with an investment of PLN 373 m (~USD 90 m).
Construction began in 2022, with completion expected in 2026.
The project has an estimated investment of PLN 373M.